After assisting the client in
addressing these problems, ETS conducted a program to flow balance each system.
After completing the system balancing, we provided a schematic with adjusted
(measured) design flows, static pressure measurements, system fan amps, and dust
collector data along with the properly adjusted damper settings for each
balanced system. This is to be used by plant as a reference for future
balancing and system maintenance activities.
As a result of this program the
client has significantly increase cartridge life thus reducing replacement
costs, has a cleaner atmosphere in the process operation area, and is more
vigilant in his approach to inspecting and maintaining his system to insure
proper operation.
Dust
Collection System EvaluationClient Food
Industry - Granulated Sugar
Description ETS
was hired by an international supplier of granulated sugar to evaluate the dust
collector systems servicing the granulated packaging and bulk and truck loading
operations at the client’s facility in the eastern region of the United States.
The reported problems for each system included reduced gas flow at the capture
hoods and high differential pressure (dP) across the baghouse. In addition
the client expressed concerns over the inability to operate the systems on a
consistent basis due to plugging of the filter elements. Included in the
ETS scope of work was a review of the system design and operational practices
and a comparison with current industry experience and accepted designs and
practices. In addition ETS was requested to provide preliminary designs
and specifications of any recommended system hardware upgrades including belt
pickups, dust capture hoods, transfer ducts, main ductwork, baghouses, and fans.
The client’s engineering group would then use the preliminary design as a basis
for the final detailed system design. The initial task in the ETS effort
was to review the design calculations and specifications of the present systems
along with any available operation and maintenance records. This task was
necessary so that we could have a complete understanding of the nature of each
systems problems and the specifics of the hardware involved.
A detailed on-site
inspection of each system was then conducted. Included in this inspection
were gas flow measurements at several points along the duct system. It was
found during this inspection that all of the long horizontal duct runs were
plugged. The plugging caused reduced gas flow throughout the ductwork
resulting in ineffective dust capture at the hoods. A comparison of the
actual versus design flow data indicated there were several inconsistencies; in
some cases the problems were caused by improper damper settings or ineffective
maintenance procedures, while in some instances the problems were caused by poor
design practices such as improper location of bucket elevator discharge pick-ups
or inadequate hood capture velocity. In addition the bags in each dust
collector inspected were found to be severely plugged.
ETS concluded that the
granulated sugar being transported in the ducts posed an unusual problem in that
it was a heavy, moist material requiring higher transport velocities than what
is typically required for industrial applications. Velocity in the duct
and the hood face (capture) velocity had to be balanced. Higher than the
required capture velocity in the hood will entrain product (that we do not want
to collect) along with the lighter dust material that we do want to collect.
On the other hand, lower than appropriately designed duct velocities will allow
the collected dust to settle in the ductwork causing dust buildup and subsequent
blockage.
ETS developed several system design options, all
of which included revised hooding and ductwork specifications along with all
pertinent velocity/volume and static pressure calculations. We also
recommended and provided a specification for a replacement fabric. This
material offered superior cake release characteristics to the fabric being used
and should alleviate the problems of clogging and fabric blinding, thus offering
significant payback in baghouse availability, reduced maintenance, reduced
baghouse pressure drop, and increased bag life.
Troubleshooting - Premature Bag Failure at
Midwestern Power Generation Station
Client Supplier
of the Air Pollution Control System
Description ETS, Inc. was
retained by a leading operating equipment manufacturer (OEM) to consult on the
issue of potential bag wear at OEM's pulse jet baghouse located at a Midwestern
power plant. The subject baghouse was of long bag design, had a two
section cage design, and employed high pressure low volume (HPLV) pulse
cleaning. The client had indicated that there was significant bag to bag
contact and it was their contention that this was the cause of a higher than
expected failure rate.
ETS personnel reviewed technical
information provided to them and inspected the unit. The ETS inspection
determined that there was a significant amount of bag to bag contact; probably
resulting from tube sheet deflection, bent cages, and imperfect cage
installation. It is further noted that bag to bag contact does not
necessarily result in premature bag wear and failure. Industry experience
has been relatively positive regarding premature bag wear as long as bag
"bumpers" and low gas velocities are employed. The client's design
employed both of these considerations at the subject facility.
Based on their findings, ETS provided
recommendations for the subject station and separate recommendations for future
units. Among the recommendations for the subject site were:
-
Document a detailed bag and cage
installation procedure.
-
Establish a bag wear monitoring
program.
-
Consider a cage alternative test
program.
The recommendations for future
installations included:
-
Lower the vertical (can) velocity to
less than 400 fpm net.
-
Establish a cage improvement program
with cage manufacturers.
-
Document a more detailed procedure
for bag and cage packing, shipping, on site handling & storage.
-
Develop a detailed in-house bag and
cage specification.
-
Review the design of the tube sheet.
-
Monitor HPLV cleaning effectiveness
versus bag length.
The client implemented most of the
recommendations and contracted ETS to consult on the future installations which
were in the design stage.
Baghouse Troubleshooting - Premature Bag
Failure
Client Electric
Utility
Description ETS was
retained to conduct an assessment of the baghouses at three of the client's
electrical generating plants to determine the causes of premature bag failure at
two of these facilities and to make corrective recommendations. The
baghouse systems at all three plants were similar in that they were of the same
design, and provided by the same supplier.
In each case the baghouse was
preceded in-line by a lime spray drier for SO2 removal. Two of
the plants had previously retrofitted their baghouse hoppers to lower the can
velocity and improve flow distribution in an attempt to lower the operating
pressure drop and reduce the potential for bag wear. The modifications
were slightly different in design and the resulting impact on bag life and
pressure drop differed. One of the facilities exhibited both reduced
pressure drop and increased bag life as a result of the modification.
Baghouse operation at this facility was not considered to be a problem and was
included in the ETS evaluation to provide insight and a basis for acceptable
performance. The design change at the second facility, while alleviating
the pressure drop concerns, had little positive effect on bag life. Bag
life in some sections of this baghouse was less than one month. Because
the bag life problem was so severe at this facility, it was decided this is
where ETS should focus on initially (problem site #1). The other problem
site (#2) had not made any modifications to the original hopper design.
This facility continued to suffer from the dual problem of unacceptable bag and
high pressure drop.
ETS conducted a site visit at problem
site #1 and inspected the baghouses. We also interviewed key plant
personnel and gathered relevant design and operational and maintenance
information. A subsequent review of the inspection report and information
was conducted and a limited number of failed bags were inspected and tested.
The results of these exercises indicated the following; (1) bag failure
was due to erosion and was almost exclusively in the bottom section of the bags;
(2) the pattern of failure was that a few rows close to the bag module inlets
was where most of the failure occurred; (3) the system was operating a higher
than design gas volume; (4) calculations of vertical flow velocity indicated
that the can velocity was significantly higher than what is considered
recommended design practice.
ETS concluded that the underlying
cause of the bag failure was an uneven distribution of the gas. This
maldistribution results in very high localized velocities which rapidly erodes
the bags. We suspected that further modification to the existing
(modified) hopper design, incorporating an improved baffle design, would
probably solve the maldistribution and thus the bag wear. Because the
issue of gas distribution design is more of an empirical art rather than a true
science, we recommended a flow model analysis should be conducted to both firm
up the nature of the existing gas distribution problem, and to optimize the
baffle design.
The client authorized ETS to conduct
the flow model, and the results of the study correlated very well with our
previous conclusions regarding distribution and failure patterns. The
modeling also provided valuable input to the baffle design and a level of
certainty that the re-design would alleviate the problem. The
modifications were made and the system has since experienced significantly
improved bag life and much lower operating costs. As a result of the
success of this project, ETS was commissioned to address the second problem
site, as well as provide bag/cage drawings and fabric specifications for all
three locations.